21. January 4, 2006.
|
|

Final exterior wall (rows 10-12) Rastra core fill.
|
|
22. January 4, 2006.
|
|

Treated 2x10 top plate with J-hook bolts embedded into the cement.
The roof trusses will connect to this top plate (with nails and hurricane clips).
|
|
23. January 23, 2006
|
|

Main trusses installed by Rick Edberg, Emmitt Fogarty & Tim Burns.
(Triple-E Construction, Belle Plaine, MN)
|
|
24. January 25, 2006
|
|

More main truss work.
|
|
25. January 26, 2006
|
|

Installing roof sheathing.
|
|
26. January 27, 2006
|
|

Peak trusses installed. These will support solar panels on the south and
allow for natural light/ventilation via remote-opening roof windows on the north.
|
|
27. January 27, 2006
|
|

North and south porches sheathed. View from the west end.
|
|
28. January 31, 2006
|
|

Roof sheathing and fascia completed.
|
|
29. February 1, 2006
|
|

North side of triangular truss: roof window curbs installed.
|
|
30. February 12, 2006
|
|

South roof face ice & water barrier installed. Shoveling off snow to facilitate
melting so roof metal can be installed.
|
|
31. February 13, 2006
|
|

Behnke Construction (Belle Plaine, MN) begins installing standing seam metal roof panels.
|
|
32. February 14, 2006
|
|

Standing seam roof metal installation, south face.
|
|
33. February 22, 2006
|
|

Standing seam roof metal installation, north face and north porch.
|
|
34. February 23, 2006
|
|

Installing north roof windows.
|
|
35.
|
|

Southwest view - south porch roof awaits replacement panels from Metal Sales.
|
|
36.
|
|

Southeast view - south porch roof awaits replacement panels from Metal Sales.
|
|
37. June 19, 2006
|
|

Plumbing work -- drain lines for laundry, utility, bathrooms.
|
|
38. June 21, 2006.
|
|

Passive Radon collection system -- river rock layer installed over packed sand bed.
|
|
39. June 22, 2006
|
|

Poly layer appled over radon rock to "trap" radon below. An open PVC-pipe is
installed within the rock layer and vented out the roof to allow radon gas to
escape to the environment, safely bypassing the home's interior.
|
|
40. June 25, 2006
|
|

Formular 250 high-density insulation sheeting installed above the radon
rock layer and below the sand bed that will store the collected solar energy.
|