41. June 25, 2006
|
|

Solar energy-storage sand bed added -- a few inches at a time, up to a depth of 6".
Compacting after a few inches, before adding more sand.
|
|
42. June 26, 2006
|
|

Sand layer compacted again before solar tubing installation begins.
|
|
43. June 26, 2006
|
|

Innovative Power Systems (Mpls, MN) begins unpacking and prepping solar panels.
|
|
44. June 26, 2006
|
|

Cleaning and prepping (soldering) copper inlets on solar panels.
|
|
46. June 26, 2006
|
|

Fourteen solar panels are carefully lifted onto the roof's two-foot wide walkway.
|
|
47. June 26, 2006
|
|

Solar panel installation.
|
|
48. June 26, 2006
|
|

Solar panel installation.
|
|
49. June 26, 2006
|
|

Solar panel installation.
|
|
50. June 26, 2006
|
|

Solar panel installation.
|
|
51. June 26, 2006
|
|

Solar panel installation.
|
|
52. June 26, 2006
|
|

A long day in the sun -- but all 14 panels are up!!
|
|
53. July 2, 2006
|
|

Another pass with the plate compactor!
|
|
54. July 2, 2006
|
|

Laying the Rehau tubing in the house. The tubes have 6" of sand below them, and the
insulation below that. Above them will be 18 more inches of sand, then the cement slab.
|
|
55. July 7, 2006
|
|

Bruce (owner/builder) pulls tubing off spool, and stabilizes the ends
by wire-tying them to a few horizontal PVC pipes at the location of the
future manifold panel and control system.
|
|
56. July 7, 2006
|
|

Tubing complete in house area.
|
|
57. July 8, 2006
|
|

Shop area tubing complete.
Randy & Jack (Deb's brother & father) surprise her by showing up to help
lay Rehau tubing. (Bruce couldn't be here today and missed all the FUN.)
|
|
58. July 12, 2006
|
|

Rehau manifold panel installed. House side.
Awaiting manifold from Goodin Company.
|
|
59. July 12, 2006
|
|

Rehau manifold panel installed. Shop side.
Awaiting manifold from Goodin Company.
|
|
60. July 13, 2006
|
|

Manifold installation (house panel).
|